Upcoming Resurfacing Work

Site at Parting Carn

The anticipated works programme for the airport and road projects is listed below:

Wednesday 18th June Preparation works raising manhole covers – Thoroughfare (day)

Thursday 19th June Resurface water main patch Buzza Street (day am)

Resurface Telegraph Road (Longstone Terrace – Parting Carn junction (day late am - pm)

Preparation works raising manhole covers – Moor Well Lane (day)

Friday 20th June Resurface Thoroughfare (day)

Runway duct crossing (night) to be identified

Saturday 21st June Resurface Telegraph Road 1 section (Parting Carn Junction towards

Porth Loo junction) (day am)

Resurface Moor Well Lane (day pm)

Runway duct crossing (night) to be identified

Excavate and fill Cargo Apron (night)

Sunday 22nd June Runway duct crossing (day & night) to be identified

Sub-base (if required) (day & night)

Lagan Construction Ltd sincerely apologises for any disturbance this essential operation causes and thanks you in advance for your co-operation and forbearance.

Please contact us on 07825 167569 if there are any problems during this work. A project update sheet which will be released soon to advise everyone on the project progress