Works to resurface St Mary's roads will begin this week.
This first section of works will see roads resurfaced in Old Town. A list of the works can be seen below.
Short Term Programme
Friday 30th May Planing & preparation works – Ennor Close
Saturday 31st May Continuation of preparation works – Ennor Close
Preparation works – 5 Islands School Car Park
Sunday 1st June Planing & preparation works – Old Town Lane (from School working towards Old Tow
Resurfacing of 5 Islands School Car Park
Monday 2nd June Planing & preparation works – Old Town Lane (through Old Town towards High Cross Lane)
Resurfacing of Ennor Close
Tuesday 3rd June Complete planning & preparation works – Old Town Lane up to High Cross Lane
Resurfacing of Old Town Lane starting from 5 Islands School
Wednesday 4th June Planing & preparation works – elsewhere – not Old Town area
Resurfacing of Old Town Lane – through Old Town
Thursday 5th June Planing & preparation works – elsewhere – not Old Town area
Resurfacing of Old Town Lane – to High Cross Lane junction
Owners co-operation is requested in moving parked cars in advance in the areas affected.
Lagan Construction Ltd sincerely apologise for any disturbance this essential work causes and thanks you in advance for your co-operation and forbearance.
Please contact us on 07825 167569 if there are any problems during this work.
A project update sheet which will be released soon to advise everyone on the project progress to date.
The St Mary’s Island Road Project is financed by the Council of the Isles of Scilly
Photo: Al Partington