This briefing explains the works that are to be done on Porthcressa and on Church Road which will be take place in the next few days. Please accept our apologies for late notification
Short Term Programme
Friday 6th June Planing & preparation works – Porthcressa
Saturday 7th June Laying of regulating course where required – Porthcressa
Commence planning & preparation works – Church Road*
Sunday 8th June Main resurfacing works – Porthcressa
Commence resurfacing works Church Road*
Continue planing & preparation works – Church Road*
Monday 9th June Contiune resurfacing works Church Road*
Continue planing & preparation works – Church Road*
Tuesday 10th June Complete resurfacing works – Church Road
*Work will be undertaken on Church Road working from Pilot’s Retreat working to St Mary’s Church. As the road is wide it will not be closed and traffic will be able to pass with care
Lagan Construction Ltd sincerely apologises for any disturbance this essential work causes and thanks you in advance for your co-operation and forbearance.
Please contact us on 07825 167569 if there are any problems during this work.
A project update sheet which will be released soon to advise everyone on the project progress to date.